Eximkey - India Export Import Policy 2004 2013 Exim Policy
4.1
Whenever a Member has reason to believe that a prohibited subsidy is being granted or maintained by another Member, such Member may request consultations with such other Member.
4.2
A request for consultations under paragraph 1 shall include a statement of available evidence with regard to the existence and nature of the subsidy in question.
4.3
Upon request for consultations under paragraph 1, the Member believed to be granting or maintaining the subsidy in, question shall enter into such consultations as quickly as possible. The purpose of the consultations shall be to clarify the facts of the situation and to arrive at a mutually agreed solution.
4.4
If no mutually agreed solution has been reached within 30 days of the request for consultations, any Member party to such consultations may refer the matter to the Dispute Settlement Body (“DSB”) for the immediate establishment of a panel, unless the DSB decides by consensus not to establish a panel.
4.5
Upon its establishment, the panel may request the assistance of the Permanent Group of Exports (referred to in this Agreement as the “PGE”) with regard to whether the measure in question is a prohibited subsidy. If so requested, the PGE shall immediately review the evidence with regard to the existence and nature of the measure in question and shall provide an opportunity for the Member applying or maintaining the measure to demonstrate that the measure in question is not a prohibited subsidy. The PGE shall report its conclusions to the panel within a time-limit determined by the panel. The PGE’s conclusions on the issue of whether or not the measure in question is a prohibited subsidy, shall be accepted by the panel without modification.
4.6
The panel shall submit its final report to the parties to the dispute. The report shall be circulated to all Members within 90 days of the date of the composition and the establishment of the panel’s terms of reference.
4.7
If the measure in question is found to be a prohibited subsidy, the panel shall recommend that the subsidizing. Member withdraw the subsidy without delay. In this regard, the panel shall specify in its recommendation the time-period within which the measure must be withdrawn.
4.8
Within 30 days of the issuance of the panel’s report to all Members, the report shall be adopted by the DSB unless one of the parties to the dispute formally notifies the DSB of its decision to appeal or the DSB decides by consensus not to adopt the report.
4.9
Where a panel report is appealed, the Appellate Body shall issue its decision within 30 days from the date when the party to the dispute formally notifies its intention to appeal. When the Appellate Body considers that it cannot provide its report within 30 days, it shall inform the DSB in writing of the reasons for the delay together with an estimate of the period within which it will submit its report. In no case shall the proceedings exceed 60 days. The appellate report shall be adopted by the DSB and unconditionally accepted by the parties to the dispute unless the DSB decides by consensus not to adopt the appellate report within 20 days following its issuance to the Members.
4.10
In the event the recommendation of the DSB is not followed within the time-period specified by the panel, which shall commence from the date of adoption of the panel’s report or the Appellate Body’s report, the DSB shall grant authorization to the complaining Member to take appropriate countermeasures, unless the DSB decides by consensus to reject the request.
4.11
In the event a party to the dispute requests arbitration under paragraph 6 of Article 22 of the Dispute Settlement Understanding (“DSU”), the arbitrator shall determine whether the countermeasures are appropriate.
4.12
For purposes of disputes conducted pursuant to this Article, except for time-periods specifically prescribed in this Article, time-periods applicable under the DSU for the conduct of such disputes shall be half the time prescribed therein.